Registration for Joint Testing of the 15' MTU Project
OKTE, a.s. invites its market participants to the coordinated testing of the 15’ MTU project on the day-ahead market at the international SDAC level, as announced by the Nemo Committee in its press release.
Market participants will be able to comprehensively test the process, scaling from submitting orders in both time granularities to evaluation of the day-ahead market in 15-minute intervals. Testing will take place via the ISOT system’s web interface, as well as external communication defined in the Technical Specification of external interfaces for market participants v1.20. For organized testing, the TEST environment will be used, which is intended for testing of pre-production versions of the XMtrade®/ISOT system.
Testing will take place from April 7, 2025, to May 15, 2025. A summary of specific testing scenarios with market participants can be found in Information package for Joint Member’s Testing Phase shared by Nemo Committee.
Registration:
An email must be sent to market@okte.sk with the subject “SDAC 15’ MTU Testing - Registration” containing the following details:
- A request for testing in the ISOT system + a valid certificate (if access to the testing environment is not set up)
- An email address for notifications during testing
If a market participant already has access to the testing environment from VDT tests in 2025, this access remains functional. However, it is still necessary to provide an email address for notifications during testing.
If a market participant does not have access to OKTE’s testing environment, they can request it by sending a Request for Testing in the XMtrade®/ISOT system, available on the OKTE website.
Registration is mandatory for participation in testing. There are no time or participant number restrictions for registration.
For any questions regarding the launch of the 15’ MTU project, you can contact market@okte.sk.