| ISOT | 2/23/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/23/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/23/2026 | Evaluation of imbalance and RE was published for 22.02.2026 - 22.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (22.02.2026 - 22.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/22/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (23.02.2026 - 23.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/22/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 23.02.2026 - 23.02.2026 was closed.
|
||||
| ISOT | 2/22/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/22/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/22/2026 | Evaluation of imbalance and RE was published for 21.02.2026 - 21.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (21.02.2026 - 21.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/21/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (22.02.2026 - 23.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/21/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 22.02.2026 - 23.02.2026 was closed.
|
||||
| ISOT | 2/21/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/21/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/21/2026 | Evaluation of imbalance and RE was published for 20.02.2026 - 20.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (20.02.2026 - 20.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/20/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (21.02.2026 - 23.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/20/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 21.02.2026 - 23.02.2026 was closed.
|
||||
| ISOT | 2/20/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/20/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/20/2026 | Evaluation of imbalance and RE was published for 19.02.2026 - 19.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (19.02.2026 - 19.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/19/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (20.02.2026 - 20.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/19/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 20.02.2026 - 20.02.2026 was closed.
|
||||
| ISOT | 2/19/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/19/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/19/2026 | Evaluation of imbalance and RE was published for 18.02.2026 - 18.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (18.02.2026 - 18.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/18/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (19.02.2026 - 19.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/18/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 19.02.2026 - 19.02.2026 was closed.
|
||||
| ISOT | 2/18/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/18/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/18/2026 | Evaluation of imbalance and RE was published for 17.02.2026 - 17.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (17.02.2026 - 17.02.2026) was published on the ISZO portal.
|
||||
| ISOT | 2/17/2026 | (IDA_JOINT_08): Delay in IDA Results publication | Others | |
|
Please be aware that the publication of the IDA Results for IDA 2 auction 18.02.2026 is delayed until further notice.
The IDA Results will be published as soon as they are available. |
||||
| ISZO | 2/17/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (18.02.2026 - 18.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/17/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 18.02.2026 - 18.02.2026 was closed.
|
||||
| ISOT | 2/17/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/17/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/17/2026 | Evaluation of imbalance and RE was published for 16.02.2026 - 16.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (16.02.2026 - 16.02.2026) was published on the ISZO portal.
|
||||
| ISOT | 2/17/2026 | IDM: (SIDC_TSO_03): XBID Ex ante information on closing of Interconnector(s) | Administration | |
|
The CEPS-50H, CEPS-APG, CEPS-PSEPLC, CEPS-TTG, CEPS-SEPS Interconnector WILL BE CLOSED on 17.02.2026 17:55 CET due to system maintenance until 17.02.2026 21:30 CET. No capacity allocation will be possible.
Another message will be sent before re-opening. |
||||
| ISZO | 2/16/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (17.02.2026 - 17.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/16/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 17.02.2026 - 17.02.2026 was closed.
|
||||
| ISOT | 2/16/2026 | SDAC_UMM_01a: Delay in final Market Coupling Results publication | Short term market results | |
|
The Market Coupling process is delayed due to technical reasons or market issues.
Therefore, the publication of the final Market Coupling Results is delayed. |
||||
| ISOT | 2/16/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/16/2026 | SDAC_ExC_02: Delay in Market Coupling Results publication | Short term market results | |
|
Please be aware that the publication of the SDAC Market Coupling Results is delayed until further notice.
The Market Coupling Results will be published as soon as they are available. If needed, another delay message will be sent out. |
||||
| ISOT | 2/16/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/16/2026 | Evaluation of imbalance and RE was published for 15.02.2026 - 15.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (15.02.2026 - 15.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/16/2026 | Adjustment of the ZP coefficient | Others | |
|
The ZP coefficient was adjusted for the month 3/2026 to value 1..
|
||||
| ISZO | 2/15/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (16.02.2026 - 16.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/15/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 16.02.2026 - 16.02.2026 was closed.
|
||||
| ISOT | 2/15/2026 | Matching results on the day-ahead market published | ||
|
The results of matching on the day-ahead market for the next business day were published.
|
||||
| ISOT | 2/15/2026 | Deadline for orders to the Short Term Market | ||
|
Was performed Deadline for orders for next business day.
|
||||
| ISZO | 2/15/2026 | Evaluation of imbalance and RE was published for 14.02.2026 - 14.02.2026 | Supply/Demand balance | |
|
Preliminary daily evaluation of imbalance and RE for the time (14.02.2026 - 14.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/14/2026 | Off-take and supply balance was published | Others | |
|
Off-take and supply balance for the trading day (15.02.2026 - 16.02.2026) was published on the ISZO portal.
|
||||
| ISZO | 2/14/2026 | Registration closure of daily diagrams | Daily diagram reception | |
|
Registration of daily diagrams for the trading day 15.02.2026 - 16.02.2026 was closed.
|
||||